In San José, cosmetic kitchen updates need no permit, like-for-like replacements of fixtures and appliances qualify for an online minor remodel permit at SJPermits.org, and anything that moves fixtures, adds fixtures, or changes walls, windows or framing is a major remodel requiring drawings and plan review.
The three categories at a glance
| Category | Examples | Permit path |
|---|---|---|
| Cosmetic | Painting, cabinet resurfacing or refacing, new flooring, new countertops | No building permit |
| Minor remodel | Replacing sink, faucet, dishwasher, range, hood or light fixtures in the same locations, with new electrical, plumbing or mechanical work, no structural changes, work limited to the kitchen | Online permit at SJPermits.org |
| Major remodel | Relocating or adding fixtures or appliances, removing or adding walls, changing windows, modifying framing | Plans submitted through the Additions & Remodels process |
This summary follows the City's own descriptions on its kitchen and bathroom minor remodel pages and its public bulletin explaining minor versus major remodels. Any improvement outside the kitchen area must be permitted separately.
Minor remodel permits on SJPermits.org
For a minor remodel, the City lets applicants select a Minor Kitchen/Bath permit, pay for it and download it online at SJPermits.org. The City recommends that a licensed contractor apply, although property owners can apply under the City's "who can apply" rules. Whoever signs the application is responsible for the work under that permit.
Once issued, you receive a permit card listing required inspections. The City asks that you:
- Keep the permit card on site for the inspector.
- Have plans and manufacturer installation instructions available.
- Provide access to all work areas, including a ladder if needed.
- Schedule inspections through SJPermits.org or by calling 408-535-3555.
Minor remodel permits are popular because they avoid plan review delays. They are not a loophole: once you move the sink six feet or add a second oven, you are in major remodel territory.
Major remodel permits
A major remodel goes through the City's Additions & Remodels process for single-family and duplex properties. You submit project plans, and staff review them for zoning, building and fire code compliance before issuing a permit. A remodel combined with an addition can be submitted as one project.
The City offers faster paths for qualifying projects:
- Over-the-counter (OTC) service for limited-scope single-family projects reviewed at the counter. City materials describe OTC as using conventional framing only, with no engineered designs or calculations, and remodel limits around 750 square feet. Remodel-only projects need a Planning clearance first.
- Residential express service for small projects that meet its size limits and comply with the California Residential Code.
- Standard plan review for projects with engineered beams, larger scopes or complexity.
A kitchen that removes a bearing wall with an engineered beam generally goes through standard review because OTC does not allow engineered designs.

What drawings usually include
For a major kitchen remodel, expect a plan set with:
- Site and floor plans showing existing and proposed layouts.
- Demolition plan identifying removed walls.
- Structural details and calculations for beams and posts, stamped by an engineer when required.
- Electrical plan with receptacles, circuits, lighting and controls.
- Plumbing and mechanical notes, including hood ducting.
- Energy compliance documents for lighting and any envelope changes.
Code updates that took effect January 1, 2026
2025 California Energy Code (Title 24, Part 6). Governs every permit application filed from January 1, 2026 onward. In kitchens, the practical impact is lighting: high-efficacy luminaires, no screw-base sockets in recessed downlights, and required controls. Your electrician fills out the lighting installation certificate.
2025 California Electrical Code. Built on the 2023 NEC. Ground-fault protection now extends to every kitchen receptacle, and island or peninsula outlets are optional but, if installed, must be on or in the countertop rather than the cabinet side.
Other 2025 California Building Standards Code parts (building, residential, plumbing, mechanical) also took effect on January 1, 2026.
Common inspection checkpoints
- Rough framing where walls change, before they are covered.
- Rough electrical: boxes, wire, circuits, GFCI and AFCI protection.
- Rough plumbing: drain, waste, vent and supply lines, often with a pressure or water test.
- Rough mechanical: hood duct and any gas line work, including gas line testing when lines are altered.
- Insulation when exterior walls are opened.
- Final: fixtures installed, appliances connected, smoke and carbon monoxide alarms as required, lighting compliance documents on site.
A City of San José inspection checklist for kitchens notes that exhaust fans must be listed for kitchen use, provide at least 100 cfm, and be ducted to the exterior with a backdraft damper.
Smoke and carbon monoxide alarms
When you pull a permit for work inside a home, California generally requires smoke alarms and carbon monoxide alarms to be installed in the required locations as a condition of final approval, even if the work is only in the kitchen. Your contractor will check existing alarms before the final inspection.
Not sure which permit you need? Ask a local remodelerFree in-home or video consult, an itemized written bid, no obligation.
HOA, historic and Eichler considerations
HOAs. Condo and townhome associations usually require their own approval before work begins. City permits do not replace HOA approval.
Historic properties. Exterior changes to City landmarks, homes in landmark districts and properties on the Historic Resources Inventory may require Planning review. Interior kitchen work typically does not.
Eichlers. The City's Eichler design standards cover outside alterations to Eichlers on its historic inventory when a Planning permit with historic review is triggered. See our Eichler kitchen guide.
What happens if you skip the permit?
Unpermitted kitchen work can surface during a sale, an insurance claim or a later remodel. Buyers' inspectors often spot new kitchens with no permit history, and fixing it later may mean opening walls for inspection. The City offers a process to legalize unpermitted work, but it is always easier to permit up front.
Who pulls the permit?
In most remodels the contractor pulls the permit, and we recommend it. It puts responsibility for code compliance on the licensed professional. If a contractor asks you to pull an owner-builder permit for work they are doing, be cautious; it can shift liability and employer obligations to you.
Permit checklist for a typical San Jose kitchen
Use this to organize your project with the contractor:
- Confirm whether the property is within San José or a neighboring jurisdiction.
- Decide whether fixtures will stay in place (minor) or move (major).
- Check HOA approval requirements and historic status for exterior changes.
- For major remodels, gather plans, engineering and energy compliance documents.
- Confirm who signs the application and pulls the permit.
- Order long-lead items while waiting for permit issuance.
- Keep the permit card, plans and manufacturer instructions on site.
- Schedule rough inspections before closing walls.
- Confirm smoke and carbon monoxide alarms before the final.
- Keep the finaled permit record for your files and future sale.
Unincorporated pockets and neighboring cities
A few unincorporated county areas remain within San José's outer boundaries, particularly in the west and east. Properties there are permitted by Santa Clara County rather than the City. Campbell, Los Gatos, Santa Clara, Saratoga and Milpitas each have their own building departments. Your address determines which office applies.
Keeping records for the future
Save permit cards, inspection records, plans and product manuals in a folder or digital archive. They help with warranty claims, insurance and future sales.
Typical permit timeline for a major remodel
Drawings and engineering usually take two to four weeks. Plan review time varies with City workload and submittal quality; small single-family projects may qualify for over-the-counter or express review, while engineered beams go through standard review. Corrections requested by plan reviewers add time, so a complete, accurate first submittal is the best way to keep the schedule moving. Order cabinets while waiting so construction can start as soon as the permit is issued.